The immediate application of the new section no. 120 TUB and the scope of its anatocism prohibition is the centre of a case-law dispute which originated from a series of inhibitory proceedings promoted by a consumer association in order to make ascertain the unlawful capitalization practiced by Banks of the passive interests in bank accounts. Now that said interim proceedings has been defined a first summary can be drawn.
Two main interpretative options so far emerged:
The Italian Government further integrated the rules applicable to debt restructuring agreements, allowing the debtor to cram down the agreement also to dissenting minority lenders, in two different frameworks: a) stand-still agreements for a “temporary moratorium” pending negotiations, and b) the actual agreements for the rescheduling and restructuring of the outstanding debt.
The Court of Siracusa (5 June 2017) ruled that a pending lease of business contract continues on a regular basis, according to the restructuring plan, in case no bids are made according to Art. 163-bis of the Italian Bankruptcy Law
The case The debtor entered into a business lease contract with a third party before he filed for concordato preventivo.
Introduction
Background
On 26 April 2016, the Italian Government has introduced a new reform to shorten the length of the recovery of credit, by approving the decree law no. 59 (the Decree), entered into force on 3 May 2016. The Decree aims at fostering and facilitating the recovery of credit throughout enforcement and insolvency proceedings.
The main innovations concern:
With the decision of 16 September 2015, No. 18131, the Court of Cassation settled a long-standing debate, ruling that the receiver can not terminate an agreement to sell real estate property, entered into by the company which is later declared bankrupt, if the purchaser has registered with the Land Registry, before bankruptcy, its claim to the Court to be transferred title to the property.
New rules for the competitive bid process aimed at the sale of the debtor’s assets in each phase or type of concordato preventivo procedure, which can now take place even before the confirmation order of the Court.
Competitive sale of debtor’s assets
With the decision No. 1195 of 18 January 2018, the Court of Cassation ruled on the powers of the extraordinary commissioner to require performance of pending contracts and on the treatment of the relevant claims of the suppliers
The case
1. Introduction
The new Regulation follows on the path of Regulation No. 1346/2000, representing the last step of a process which has been started years ago. European Union authorities resorted also to other means in this direction: aside to the Regulation, a Recommendation has been issued in 2014, inviting Member States to adopt internal procedures more favourable to restructuring (rather than liquidating) distressed businesses.
Il Tribunale di Milano (10 novembre 2016) ha disposto l’omologazione ex art. 182-bis l.fall. richiesta da un fondo, ritenuto soggetto di diritto autonomo rispetto alla SGR per mezzo della quale agisce e non solo un patrimonio separato
Il caso
Una SGR ha chiesto l’omologazione di un accordo di ristrutturazione dei debiti per conto di un fondo comune di investimento immobiliare di tipo chiuso, deducendone la situazione di incapienza patrimoniale.