The Third Circuit Court of Appeals recently affirmed the District Court’s ruling in In re Philadelphia Newspapers, LLC.1 The Court allowed Philadelphia Newspapers, LLC to require all-cash bids for the asset sale under their proposed plan. This precluded secured creditors from credit bidding, as long as the plan provided those creditors with the “indubitable equivalent” of the value of their claims.
Last month, in a significant ruling in the General Growth Properties, Inc. (“GGP”) bankruptcy case, the United States Bankruptcy Court for the Southern District of New York denied motions to dismiss, as bad faith filings, the bankruptcy cases of 20 purported bankruptcyremote special purpose entity (“SPE”) subsidiary debtors.1
Our May 11th memo entitled “General Growth Properties Bankruptcy Court Defers Final Ruling on Cash Collateral, Cash Management and DIP Financing Issues” concluded that the ultimate impact of the bankruptcy filings of General Growth Properties, Inc. and its affiliates would depend in large part on how the cash collateral and DIP Loan issues were resolved. On May 13th, Judge Allan L. Gropper, the U.S. Bankruptcy Judge before whom these bankruptcies are pending, entered final orders on the pending cash collateral, cash management and debtor-in-possession financing motions.
In In re River Center Holdings, LLC,1 the United States Bankruptcy Court for the Southern District of New York refused to permit lenders to enforce an oral commitment of the debtors’ principal to fund certain litigation. In River Center, the debtors’ principal had stated at a hearing that he would fund a condemnation action relating to property that served as collateral for the lenders’ financing.
Introduction
In Oneida Ltd. v. Pension Benefit Guaranty Corp. (In re Oneida Ltd.),1 the United States Bankruptcy Court for the Southern District of New York addressed whether a premium payment created by the Deficit Reduction Act of 2005 (“DRA”)2 for pension plans terminated as part of a chapter 11 restructuring is a pre-petition claim or a post-petition administrative expense. The Court held that the statutorily mandated premium payment was a contingent pre-petition claim and was discharged upon confirmation of the debtor’s plan.
Late last year, government responses to the subprime mortgage crisis proliferated but most attention focused on those measures that could be, and in some cases were, rapidly implemented — measures like the Treasury Department’s urging holders of certain subprime adjustable rate mortgages (ARMs) to freeze interest rates temporarily or the Federal Reserve’s proposed tightening of lending requirements.
CAYMAN ISLANDS
On January 14, 2014, Judge Robert E. Gerber of the United States Bankruptcy Court for the Southern District of New York in Weisfelner v. Fund 1. (In re Lyondell Chemical Co.), Adv. Proc. No. 10-4609 (REG), 2014 WL 118036 (Bankr. S.D.N.Y. Jan.
On Nov. 28, 2012, the U.S. Court of Appeals for the Fifth Circuit in In re Vitro S.A.B. de C.V. issued a groundbreaking decision under Chapter 15 of the Bankruptcy Code, which provides the mechanics for U.S. bankruptcy courts to deal with cross-border insolvency proceedings. Although deference to judgments of foreign courts is the norm under Chapter 15, in this instance the Fifth Circuit refused to enforce a court-approved Mexican plan of reorganization on the ground that it contained non-consensual non-debtor releases of noteholders’ claims against the debtor’s non-debtor subsidiaries.
On August 2, 2012, the United States Court of Appeals for the Fifth Circuit held that a requirements contract for electricity is a forward contract for purposes of section 546(e) of the Bankruptcy Code and, therefore, settlement payments made under the contract are exempt from avoidance as preferences. Claude Lightfoot v.