Fulltext Search

A Singaporean construction company in liquidation has successfully sued one of its former directors for failing to act in the best interests of the company, highlighting the importance of directors being aware of, and protecting against, potential personal liability for breach of duty.

Directors’ liability – the risk

A worldwide moratorium is one of the most important protections and tools available to a debtor in the Singapore cross-border restructuring regime. A recent Singapore High Court case, Re: Zetta Jet Pte Ltd and Others (Asia Aviation Holdings Pte Ltd, intervener) [2019] SGHC 53 ("Re Zetta Jet (2)"), highlighted some important considerations relating to such a worldwide moratorium, in particular dealing with potential conflicts between different jurisdictions.

Singapore's Cross-border Restructuring Regime

As more Turkish companies begin to report liquidity issues and economic pressures begin to bite, successful financial restructurings are likely to become increasingly critical to the prosperity of the Turkish economy

Only time will tell whether local processes will provide a suitable toolkit for large-scale corporate restructurings, or whether other international restructurings processes may also have a role to play.

What is a Statutory Demand?

A Statutory Demand is a formal 21-day demand for payment issued by a creditor to a debtor.

When can a Statutory Demand be issued?

You can issue a Statutory Demand if your debt is owed from a limited company or an LLP and is a liquidated sum of more than £750 or when a creditor is owed a debt from an individual, a sole trader or a partnership as long as the debt is for a liquidated sum of more than £5000 and is unsecured.

In 2018 the Insolvency Service recorded that Company insolvencies were at their highest level since 2014, with a slight increase of 0.7% on 2017. Individual insolvencies were also at their highest level since 2011 with an increase of 16.2% on2017. There was a 19.9% increase on Individual Voluntary Arrangements (“IVAs”) which is the highest level ever recorded. With this in mind, businesses need to focus on tight cash flow across all areas and understand the importance of putting a credit policy in place.

The High Court of England & Wales considered, in respect of the delayed completion of a solar project, the appropriate end date for liquidated damages under a terminated construction contract.

It is usual and standard for a construction contract to contain a liquidated damages clause. It is also common for a termination clause to be included and it is not unusual for it to be exercised. Strangely, however, it is not clear under English law how these two concepts interact.

All three institutions of the European Union have now approved the EU Preventive Restructuring Framework Directive. This is the EU's first attempt to "harmonise" insolvency laws across the Member States, that have disparate existing legislation. What does the Directive do and what will be its effect in practice?

The Directive

In a noteworthy decision to participants in the energy industry, the High Court of England & Wales examined what constitutes a valid liquidated damages clause in the event of delayed completion of a solar project. And last week in Singapore, the High Court considered the enforceability of liquidated damages provisions on termination of power purchase agreements.

Goodbye 2018 and hello 2019! It is that time of year to take stock and review your cash flow for 2019.

The Court of Appeal has issued a welcome clarification of rules regulating the payment of dividends to shareholders in Global Corporate Ltd v Hale [2018] EWCA Civ 2618.

Facts

The case was appealed from the ruling of Judge Matthews in the High Court [2017] EWHC 2277 (Ch). At issue were several payments made by Powerstation UK Limited (the “Company”) to Mr Hale, who was a director and shareholder of the Company at the relevant times.