In recent weeks, the dispute in Windstream’s bankruptcy between Windstream and its REIT spinoff Uniti Group over the lease transaction that ultimately led to Windstream’s chapter 11 bankruptcy has continued to escalate with Windstream filing an adversary complaint against Uniti. In its complaint, Windstream seeks to recharacterize the lease as a disguised financing alleging that the lease resulted in a long-term transfer of billions of dollars to Uniti to the detriment of Windstream’s creditors.
On April 23, 2019, the United States District Court for the Southern District of New York, in fraudulent transfer litigation arising out of the 2007 leveraged buyout of the Tribune Company,1 ruled on one of the significant issues left unresolved by the US Supreme Court in its Merit Management decision last year.
Intercreditor agreements--contracts that lay out the respective rights, obligations and priorities of different classes of creditors--play an increasingly important role in corporate finance in light of the continued prevalence of complex capital structures involving various levels of debt. When a company encounters financial difficulties, intercreditor agreements become all the more important, as competing classes of creditors seek to maximize their share of the company's limited assets.
On January 17, 2017, in a long-awaited decision in Marblegate Asset Management, LLC v. Education Management Finance Corp.,1 the US Court of Appeals for the Second Circuit held that Section 316 of the Trust Indenture Act ("TIA") does not prohibit an out of court restructuring of corporate bonds so long as an indenture's core payment terms are left intact.
On December 5, 2013, Judge Steven Rhodes of the US Bankruptcy Court for the Eastern District of Michigan held that the city of Detroit had satisfied the five expressly delineated eligibility requirements for filing under Chapter 9 of the US Bankruptcy Code1 and so could proceed with its bankruptcy case.
What happens if one party to a contract fails to perform? Can the innocent party get all of its losses back? What happens if the losses are difficult to prove?
Here, we look at what you can claim and how to protect your position.
The general rule
Damages for breach of contract are usually intended to compensate the injured party for its losses arising naturally from the breach or which were within the parties' contemplation when the contract was made.
In the case of William Hare Ltd v Shepherd Construction Ltd [2009] EWHC 1603 (TCC) (25 June 2009), the court declined to incorporate amendments made to an Act before the contract was signed which were not specifically referred to in the contract.
The facts