The Court of Bergamo (23 December 2015) authorized a business lease agreement even though a previous public auction could not be held due to the urgency of the case, considering that the mandatory provisions of Art. 163-‐bis of the Italian Bankruptcy Law apply only if consistent with the “pre-‐ concordato” phase.
The case
The Supreme Court (decision No. 20559 of 13 October 2015), decided that a single application for admission to theprocedure is not admissible if it involves a group, with a single proposal for all the creditors of the different companies,although the relevant assets and liabilities are kept formally separated.
The case
The Tribunal of Milan with a decree of 17 September 2015 ruled that the enforcement of a bank guarantee, pending therequest by the debtor to authorize the stay or termination of the same in a concordato preventivo procedure, bars thedecision by the Tribunal
The case
With the decision of 16 September 2015, No. 18131, the Court of Cassation settled a long-standing debate, ruling that the receiver can not terminate an agreement to sell real estate property, entered into by the company which is later declared bankrupt, if the purchaser has registered with the Land Registry, before bankruptcy, its claim to the Court to be transferred title to the property.
The immediate application of the new section no. 120 TUB and the scope of its anatocism prohibition is the centre of a case-law dispute which originated from a series of inhibitory proceedings promoted by a consumer association in order to make ascertain the unlawful capitalization practiced by Banks of the passive interests in bank accounts. Now that said interim proceedings has been defined a first summary can be drawn.
Two main interpretative options so far emerged:
Con il D.Lgs. 180/2015 e D.Lgs. 181/2015 è stata recepita la direttiva 2014/59/UE (c.d. “Direttiva BRRD”Bank Recovery and Resolution Directive) che istituisce un quadro di risanamento e di risoluzione deglienti creditizi e delle imprese di investimento
Premessa
Lawmakers introduce further measures in order to stimulate new loans after the pre-filing for concordato preventivo or for a debt restructuring agreement, when it is urgent to prevent an unrecoverable prejudice to the business
The context
The Tribunal of Modena with a decision of 6 June 2015 stated that a supplier can not refuse to perform its obligation and ask for the payment of previous claims by raising a non-fulfilment of the debtor’s obligations objection. Payment of such claims can then be made only after confirmation of the concordato by the Court.
The case
The Tribunal of Milan, with a decision of 5 May 2015, ruled that Art. 104-ter of the Italian Bankruptcy Law is applicable to the lease of business entered into before the declaration of bankruptcy and, therefore, the receiver can terminate pending contracts according to Art. 72 of the Italian Bankruptcy Law
The case
With the decision of 2 September 2015, No. 17461, the Court of Cassation confirmed that secured creditors’ deferred payment amounts to a partial satisfaction and has confirmed the criteria for determining the economic loss arising out of the delay, for allowing these creditors to vote.