On 10 October 2019 the Australian Small Business and Family Enterprise Ombudsman, Kate Carnell, announced an upcoming inquiry into insolvency practices. The inquiry was announced in light of rising concerns as to the efficacy of the voluntary administration process for SMEs and family-owned businesses, and concerns with the conduct of insolvency practitioners more generally.
The Ministry of Business, Innovation and Employment has published a Cabinet Paper outlining proposed reforms to New Zealand's insolvency laws to take account of certain recommendations made in the second report of the Insolvency Working Group from May 2017.
On August 9, 2019, in a unanimous decision (written by a former bankruptcy judge), the Eighth Circuit Court of Appeals affirmed the confirmation of the Peabody Energy Chapter 11 plan (“Plan”)1 with a prominent backstopped rights offering component.
Non-party costs are exceptional and are only awarded when it is just to do so and when 'something more' about the non-party's conduct warrants costs. The involvement of a parent company in litigation and avoiding a realistic settlement is an example of the 'something more' requirement being met. In Minister of Education v H Construction North Island Ltd (in req and liq) [2019] NZHC 1459, the High Court found that McConnell Ltd's (McConnell) actions in this litigation warranted awarding non-party costs and disbursements of over a million dollars.
In Mission Product Holdings, the Supreme Court Endorses “Rejection-as-Breach” Rule and Interprets Broadly the Contract Rights that Survive Rejection
Last year, the Supreme Court issued its decision in Merit, unanimously ruling that a buyout transaction between private parties did not qualify for “safe harbor” protection under Bankruptcy Code section 546(e), on the basis that a “financial institution” acted as an intermediary in the overarching transaction.
On March 18, 2019, Judge Stuart M. Bernstein of the United States Bankruptcy Court for the Southern District of New York issued a decision enforcing a mortgage lender’s claim for a prepayment premium (a/k/a make-whole or yield maintenance premium) notwithstanding the lender’s prepetition acceleration of the loan due to the debtor’s default.
On various occasions during the periods 2012 to 2018, Shane Warner Builders Limited (SWBL) regularly failed to pay GST and PAYE to the Commissioner of Inland Revenue.
In January 2018 the Commissioner filed an application to put SWBL into liquidation. The proceeding was adjourned in March 2018 whilst the Commissioner and Applicant engaged in negotiations for relief which ultimately failed due to SWBL's history of failures to pay tax arrears and failing to provide substantive supporting evidence regarding the source of funds required to settle current tax arrears.
North Harbour Motors Limited (in liquidation) (North Harbour) issued a statutory demand against Moffat Road Limited (Moffat) in respect of two separate $30,000 deposits paid by North Harbour to Moffat on the purchase of two properties pursuant to agreements for sale and purchase dated 6 July 2015 (the Agreements).
FTG Securities Limited involved an application by FTG Securities Limited (FTG) for declarations as to the interpretation of a Deed of Priority. The Deed of Priority was entered into by Canterbury Finance Limited (CFL) and a bank with respect to the security interests in Tuam Ventures Limited (in Rec and in Liq) (TVL). Declaratory relief was sought against the bank and the receivers of TVL. An issue raised by way of an affirmative defence was whether the assignment of TVL's debt and securities to FTG is valid from a technical legal perspective and therefore wh