On April 12, 2024, the U.S. Supreme Court issued an important decision in the case of Macquarie Infrastructure Corp. v. Moab Partners, L.P., No. 22-1165. Justice Sotomayor, writing for a unanimous Court, ruled that “pure omissions are not actionable under Rule 10b-5(b).” In other words, a pure omission (i.e., where a speaker says nothing) cannot support a private claim under Section 10(b) of the Securities Exchange Act of 1934 (the “Exchange Act”) and Rule 10b–5, even if such an omission could constitute a violation of Item 303 of Regulation S-K (“Item 303”).

Summary

In the first appeal of a restructuring plan under Part 26A Companies Act 2006, the English Court of Appeal unanimously set aside the first instance decision sanctioning the plan proposed by AGPS BondCo PLC, part of the Adler real estate group1.

Summary

Trustees and officeholders (such as administrators, receivers and liquidators) can ask the Court to approve steps that they propose to take in the administration of their estate (such as the sale of an asset or settlement of a claim).

The Court1 exercised its discretion to sanction a restructuring plan proposed by AGPS BondCo PLC (the Company) (part of the Adler real estate group) to amend indebtedness arising under six series of senior unsecured notes governed by German law, which matured on different dates through to 2029.

In vielen Branchen kann die Lieferkette eine Vielzahl von Unternehmen und Jurisdiktionen umfassen. Im derzeitigen Wirtschaftsklima ist es nicht ungewöhnlich, dass einzelne Lieferanten innerhalb dieser Lieferkette in finanzielle   Schwierigkeiten   geraten   oder ein Insolvenzverfahren beantragen.

In many industries, the supply chain can involve multiple suppliers and jurisdictions. In the current economic climate, it is not unusual for a supplier within the supply chain to encounter financial distress or even to enter into formal insolvency proceedings. This can have a significant impact on a company if its business depends on a distressed supplier and an alternative or additional supplier cannot be found (and production cannot be brought in house) or an alternative sourcing is not possible for other reasons, like part/raw material approval process, testing, customs etc.

This article first appeared in Accountancy Daily on 20 January 2023.

With supply chain problems, war in Europe and other issues leading to higher inflation and an increasingly uncertain economic outlook, this article explores the options available to companies experiencing financial distress.