Fulltext Search

This week’s TGIF considers a recent decision of the Supreme Court of New South Wales (Forex Capital Trading Pty Ltd (in liquidation) v Invesus Group Limited [2024] NSWSC 867). Justice Ball determined that admission of a proof of debt by a liquidator was not akin to a judgment or settlement, and that such an admission did not create a new liability of the company.

In a recent decision of the Supreme Court of New South Wales (In the matter of Pacific Plumbing Group Pty Limited (in liquidation) [2024] NSWSC 525), Justice Black determined that a payment made by a third party was not an unfair preference because the payment did not diminish assets available to creditors.

Key Takeaways

The Federal Court in Morgan, in the matter of Traditional Values Management Limited (in liq)[2024] FCA 74, approved an abridged process that allowed the liquidator to admit debts of a group of unsecured creditors without requiring a formal proof of debt.

Key Takeaways

In this week’s TGIF, we consider the Court of Appeal’s decision in Anchorage Capital Master Offshore Ltd v Sparkes [2023] NSWCA 88 and the challenges faced by lenders in accepting representations as to solvency and the financial position of borrowers.

Key takeaways

This week’s, TGIF considers the Court of Appeal’s decision in Westgem Investments Pty Ltd v Commonwealth Bank of Australia Ltd [2022] WASCA 132, handed down on 4 November 2022 in favour of the Commonwealth Bank of Australia Ltd and Lloyds Banking Group (Financiers).

Key takeaways

It is common for construction project owners to finance projects through multiple mortgages, especially in times of rising construction costs. However, when an insolvency situation arises, holdback priority claims from contractors and subcontractors are particularly complex when there are multiple building mortgages involved. The Ontario Superior Court (Commercial List) provided new clarity in this regard in its April 29, 2022 decision in BCIMC Construction Fund Corp. et al.

Understanding limitation periods are of crucial importance in the construction industry, particularly when a contractor is faced with unpaid invoices for services or materials rendered. The Ontario Court of Appeal stepped back into the spotlight in this regard with its decision in Thermal Exchange Service Inc. v Metropolitan Toronto Condominium Corporation No. 1289, 2022 ONCA 186, in holding that a defendant's assurances may prolong the "discoverability" of a claim for non-payment.

Background