In a recent case, the Victorian Supreme Court said that an accountant ‘would know well that a statutory demand involves strict time frames for response and potentially very significant consequences for a company’. The accountant failed to take appropriate steps to inform the company of the statutory demand.

The statutory demand process

If a company does not comply with a statutory demand within 21 days of service, it is deemed to be insolvent and the creditor may proceed to wind up the company.

A recent court decision considers the legal principles and sufficiency of evidence when a court-appointed receiver seeks approval of their remuneration.

A court-appointed receiver needs court approval for the payment of their remuneration. The receiver has the onus of establishing the reasonableness of the work performed and of the remuneration sought.

This article will look at the recent decision of David Doyle J in In the Matter of HQP Corporation Limited (in Official Liquidation) (7 July 2023) and its effect on the ability of investors to recover damages from a company in which they have acquired shares as a result of a fraudulent misrepresentation.

Introduction

The case involved an application by liquidators for direction in relation to three issues in the winding up of the Company:

On 6 October 2023, Parker J handed down his reasons for dismissing an application to bring the voluntary liquidation of Port Link GP Ltd, General Partner (GP) of The Port Fund L.P. (TPF) under the supervision of the Grand Court pursuant to section 124 of the Companies Act. (Section 124)

The illegality defence (which aims to prevent a party benefiting from its illegal conduct via legal claims) has been the subject of considerable judicial analysis in commonwealth jurisdictions in recent years.

A Supreme Court in Australia has dismissed an application by a UK company’s moratorium restructuring practitioners for recognition of a UK moratorium and ordered that the company be wound up under Australian law.

The decision provides insights into the interaction between cross-border insolvencies and the winding up in Australia of foreign companies under Australian law.

Introduction

In the matter of Hydrodec Group Plc [2021] NSWSC 755, delivered 24 June 2021, the New South Wales Supreme Court: