As from 1 May 2018, the Belgian insolvency landscape will look different following the entry into force of the brand new Insolvency Law (Book XX of the Economic Law Code). In the wake of the electronic debt reporting system that came into force on 1 April 2017, the filing of bankruptcy must also be made electronically in the Central Solvency Register (RegSol) as of 1 May 2018.
Vanaf 1 mei 2018 ziet het Belgische insolventielandschap er anders uit ingevolge de inwerkingtreding van het gloednieuwe insolventierecht (Boek XX in het Wetboek Economisch Recht). In navolging van de elektronische aangifte van schuldvordering sinds 1 april 2017, dient vanaf 1 mei 2018 ook de aangifte van faillissement elektronisch te gebeuren in het Centraal Register Solvabiliteit (Regsol).
L’entrée en vigueur de la toute nouvelle loi sur l’insolvabilité modifiera le paysage du droit de l’insolvabilité belge dès à partir du 1er mai 2018. Le 1er avril 2017 entrait en vigueur le système de déclaration de créance par voie électronique. A présent, entrera en vigueur, dès ce 1er mai 2018, la demande de faillite par voie électronique dans le Registre Central de la Solvabilité.
Speed read
The British government has commenced an airline insolvency review, in the wake of recent high profile airline failures such as Monarch and Air Berlin, and on the premise that changes in the industry have outpaced protection regimes.
The review will focus on two main areas: repatriation of stranded passengers and redress for consumers. There is a desire to minimise repatriation costs falling on the public purse and ensure that consumers have clear avenues of redress.
We closed the first quarter of 2018 following a period of intense scrutiny on the restructuring and insolvency profession. The stress in the retail and dining sectors, the increase in CVAs and the various attendances of stakeholders in the profession before Select Committees has been the forerunner to two consultation papers.
Sellers and suppliers of movable assets can deal with problems caused by poorly-paying customers through a retention of title clause. This clause makes it contractually possible to stipulate that ownership of a certain good does not transfer until the third party acquirer has paid the full price.
It is interesting to note that the new Law on Pledges has created a better legal framework for the retention of title clause, putting any creditor - assuming a retention of title clause has been included - in a stronger position.
The Inner House of the Court of Session has found that, where a business had no realistic prospect of continuing in existence, it was not appropriate to assess whether a property was sold at an undervalue by reference to a forced sale valuation.
The Court’s judgment serves as a valuable reminder of some fundamental principles of insolvency law.
The facts
A recent TCC decision has concluded that the contractor insolvency provisions of the JCT form continue to apply after a termination by the contractor for repudiation. This conclusion may give rise to surprising results and potentially allow an employer to claim from the contractor additional amounts incurred in completing the works with a third party even after termination for the employer’s own default and/or repudiation.
In Hellas Telecommunications (Luxembourg) [2017] EWHC 3465 (Ch), the High Court ordered respondent liquidators to disclose the identity of third-party litigation funders and the terms on which funding was provided in order to facilitate an application for security of costs.
Facts
November 2017 saw the first successful pre-packaged bankruptcy of a wind farm operator following the introduction of this procedure to Polish bankruptcy law in January 2016. Thanks to a decision made by the bankruptcy court in Warsaw, the assets of the 6 MW wind farm in Korzęcin can now be taken over by a publicly listed company operating in the renewable energy sector.