Khandanpour v Chambers [2019] EWCA Civ 570

Should relief from sanctions be granted where a judgment debtor purports to appropriate monies paid to satisfying a procedural condition for setting aside a default costs order, but the creditor purports to appropriate the monies instead to the judgment debt?

Background

On March 26, 2019, the First Circuit Court of Appeals, affirming a decision by the District Court emanating out of the Puerto Rico Title III bankruptcy cases, found that Sections 928(a) and 922(d) of the Bankruptcy Code “permit, but do not require, continued payment during the pendency of the bankruptcy proceedings.”[i] The First Circuit found that these provisions pr

How deep is the “pool of facts in which it is permissible to fish for the basis of the new cause of action” if a party wishes to benefit from the ‘relation back’ doctrine when calculating limitation periods? The Court of Appeal gives guidance on the meaning of “the same or substantially the same facts” for the purpose of CPR r 17.4(2).

On February 14, 2019, Judge Lane of the Bankruptcy Court for the SDNY issued an opinion in Republic Airways Holdings Inc. addressing whether the liquidated damages provisions in certain aircraft “true leases” under Article 2A of the New York UCC were enforceable and, if not, whether they would still be enforceable against the debtor-guarantor of the leases.

With the Court of Appeal’s decision in Bresco Electrical Services Ltd v Michael J Lonsdale (Electrical) Ltd just a few weeks old, it is hardly surprising that people are looking again at the relationship between insolvency law and adjudication, noting that in cases of liquidation where parties have a cross claim, construction law defers to insolvency law.

This was clearly illustrated in Gregg Nowak Ltd v CSS Electrical Distributors Ltd, which came before HHJ Bailey earlier this month.

Background

This was a conjoined appeal alongside Bresco v Lonsdale. In this case, Cannon and Primus had already participated in an adjudication, with the decision of the adjudicator favouring Primus. Primus would later enter into a Company Voluntary Arrangement.

The CVA was made on the basis that, although Primus was insolvent at the time, it would be able to satisfy its creditors if it were able to recover from Cannon and other third parties through litigation and adjudication. This was preferable to liquidation.

On January 29th, PG&E Corporation and its regulated utility subsidiary, Pacific Gas and Electricity Company (collectively, “PG&E”), commenced bankruptcy cases in the Bankruptcy Court for the Northern District of California. Here are nine things to watch for in the PG&E bankruptcy.

Insolvency Set-Off and Construction Contract Adjudications in light of Bresco Electrical Services Ltd (in liquidation) v Michael J Lonsdale (electrical) Ltd; Cannon Corporate Ltd v Primus Build Ltd [2019] EWCA Civ 27

This case concerned both the appeal in Bresco v Lonsdale and Cannon Corporate v Primus Build. The present case comment is only concerned with the former.

Background

Bresco appealed to set aside the order of an injunction from Fraser J. That injunction prevented the continuation of an adjudication in which Bresco and Lonsdale (in liquidation) sought sums from each other in claims and cross-claims.