The Court of Milan (19 February 2016) adopts a restrictive approach and rules out that the special rulesprovided for concordato “preserving the business” (“concordato con continuità aziendale”) can applywhere the plan includes a lease of business arrangement
The case
A corporation’s asset sale “was structured [by its insiders] so as to fraudulently transfer assets in order to avoid paying [a major creditor] what it was owed,” held the U.S. Court of Appeals for the Seventh Circuit on March 22, 2016. Continental Casualty Co. v. Symons, 2016 WL 1118566, at *6 (7th Cir., March 22, 2016).
Creditors of a Chapter 11 debtor asserting “state law, constructive fraudulent [transfer] claims … are preempted by Bankruptcy Code Section 546(e),” held the U.S. Court of Appeals for the Second Circuit on March 29, 2016. In re Tribune Company Fraudulent Conveyance Litigation, 2016 WL ____, at *1 (2d Cir. March 29, 2016), as corrected.
A Chapter 11 debtor’s pre-bankruptcy “surrender of [two] … leases to [its landlord] could be regarded as a preferential transfer,” held the U.S. Court of Appeals for the Seventh Circuit on March 11, 2016. In re Great Lakes Quick Lube LP, 2016 WL 930298, at *2 (7th Cir. March 11, 2016).
While a recent federal bankruptcy court ruling provides some clarity as to how midstream gathering agreements may be treated in Chapter 11 cases involving oil and gas exploration and production companies (“E&Ps”), there are still many questions that remain. This Alert analyzes and answers 10 important questions raised by the In re Sabine Oil & Gas Corporation decision of March 8, 2016.[1]
The release provisions in a corporate debtor’s Chapter 11 plan were “not sufficiently specific to release” a plaintiff’s Fair Labor Standards Act (“FLSA”) claim against the debtor’s president (“P”), held the U.S. Court of Appeals for the Fifth Circuit on Jan. 6, 2016. Hernandez v. Larry Miller Roofing, Inc., 2016 WL 67217, at *4 (5th Cir. Jan. 6, 2016).
The Court of Bergamo (23 December 2015) authorized a business lease agreement even though a previous public auction could not be held due to the urgency of the case, considering that the mandatory provisions of Art. 163-‐bis of the Italian Bankruptcy Law apply only if consistent with the “pre-‐ concordato” phase.
The case
The Court of Alessandria (18 January 2016) addressed a series of issues regarding various rules meant to allow preserving the business in the concordato preventivo procedure, sell the business through competitive bids, lease the business prior to the application to commence the procedure, "mixed" concordato schemes and objections which key continuing suppliers can raise for past debts
The case
The Italian Government started the legislative process for a comprehensive restatement of the whole set of rules of insolvency procedures, with specific innovative addresses regarding (to mention only the most important) the concordato preventivo procedure, venue rules, an out-of-court mediation alert process to timely address a risk of insolvency, new forms of security and a streamlined se
Il Governo prevede una riformulazione complessiva ed organica della disciplina delle procedure di insolvenza esistenti, sulla linea dell‘evoluzione più recente, con precisi indirizzi innovativi – tra i più rilevanti – in tema di concordato preventivo di gruppo e liquidatorio, concentrazione della competenza dei tribunali, composizione assistita della crisi, riordino dei privilegi e nuove forme di garanzia
Premessa