In Diamond Z Trailer, Inc. v. JZ, LLC (In re JZ, LLC), No. 07-1011 (9th Cir. B.A.P., June 18, 2007), the Ninth Circuit Bankruptcy Appellate Panel affirmed a Bankruptcy Court decision holding that an unscheduled executory contract rides through the bankruptcy if not assumed or rejected during the bankruptcy. Further, a debtor has standing to sue for a breach of that executory contract when the breach occurred after the closure of the bankruptcy case.
In the case of Sherman v. Harbin (In re Harbin), the Ninth Circuit decided that in determining the feasibility of a plan under Bankruptcy Code Section 1129(a)(11), a court must evaluate the possible impact of pending litigation, whether at the trial level or on appeal.
In Travelers Cas. and Sur. Co. of America v. Pacific Gas & Electric Co., 127 S. Ct. 199 (2007) ("Travelers"), the United States Supreme Court overturned a Ninth Circuit Court of Appeals opinion that had made pre-petition contractual provisions awarding attorneys' fees to the prevailing party unenforceable in bankruptcy to the extent the parties litigated issues peculiar to bankruptcy law. The Ninth Circuit opinion, Fobian v. Western Farm Credit Bank (In re Fobian), 951 F.2d 1149 (9th Cir.
On March 7, 2007, the Second Circuit Court of Appeals held that "in the Chapter 11 context, whether a pre-plan settlement's distribution plan complies with the Bankruptcy Code's priority scheme will be the most important factor for a Bankruptcy Court to Consider in approving a settlement under Bankruptcy Rule 9019." In re Iridium Operating LLC, No. 05-2236 (2d Cir. March 7, 2007)