Fulltext Search

We're often asked to advise on what is the appropriate level of liquidated damages for delay in a building contract. Whilst this is a commercial issue and therefore outside the remit of legal advice there are some principles relating to the application of liquidated damages that we can bring to the parties' attention.

In the matter of Bleecker Property Group Pty Ltd (In Liquidation) [2023] NSWSC 1071, appears to be the first published case that considers the question of whether an order can be made under section 588FF(1)(a) of the Corporations Act 2001 (Cth) by way of default judgment against one defendant where there are multiple defendants in the proceedings.

Key takeaways

Modular construction has been heralded for several years now as a construction methodology that saves time, reduces waste and minimises cost. It is therefore unsurprising that modular construction forms part of the various "modern methods of construction" that are now being encouraged by the UK Government. Use of modular construction can range from isolated elements like bathroom pods to where the majority of the building is comprised of modules and is commonly encountered in housing, student accommodation and hotels.

This week’s TGIF considers Hundy (liquidator), in the matter of 3 Property Group 13 Pty Ltd (in liquidation) [2022] FCA 1216, in which the Federal Court of Australia granted leave under rule 2.13(1) of the Federal Court (Corporations) Rules 2000 (Cth) (FCCR) for intervening parties to be h

In bankruptcy as in federal jurisprudence generally, to characterize something with the near-epithet of “federal common law” virtually dooms it to rejection.

In January 2020 we reported that, after the reconsideration suggested by two Supreme Court justices and revisions to account for the Supreme Court’s Merit Management decision,[1] the Court of Appeals for the Second Circuit stood by its origina

The majority of the building and engineering contracts that we encounter (and draft) require some form of performance security from the contractor, whether this is a parent company performance guarantee granted by the contractor's ultimate holding company, or a performance bond granted by a third party surety or a bank for a capped sum. Indeed most, if not all, standard form contracts provide for these forms of security, even if only as an option.

It seems to be a common misunderstanding, even among lawyers who are not bankruptcy lawyers, that litigation in federal bankruptcy court consists largely or even exclusively of disputes about the avoidance of transactions as preferential or fraudulent, the allowance of claims and the confirmation of plans of reorganization. However, with a jurisdictional reach that encompasses “all civil proceedings . . .

I don’t know if Congress foresaw, when it enacted new Subchapter V of Chapter 11 of the Code[1] in the Small Business Reorganization Act of 2019 (“SBRA”), that debtors in pending cases would seek to convert or redesignate their cases as Subchapter V cases when SBRA became effective on February 19, 2020, but it was foreseeable.

Our February 26 post [1] reported on the first case dealing with the question whether a debtor in a pending Chapter 11 case may redesignate it as a case under Subchapter V, [2] the new subchapter of Chapter 11 adopted by the Small Business Reorganization Act of 2019 (“SBRA”), which became effective on February 19.