In a recent case, the Victorian Supreme Court said that an accountant ‘would know well that a statutory demand involves strict time frames for response and potentially very significant consequences for a company’. The accountant failed to take appropriate steps to inform the company of the statutory demand.
The statutory demand process
If a company does not comply with a statutory demand within 21 days of service, it is deemed to be insolvent and the creditor may proceed to wind up the company.
A recent court decision considers the legal principles and sufficiency of evidence when a court-appointed receiver seeks approval of their remuneration.
A court-appointed receiver needs court approval for the payment of their remuneration. The receiver has the onus of establishing the reasonableness of the work performed and of the remuneration sought.
Re: Guangdong Overseas Construction Corporation () (in liquidation) (date of decision: 17 May 2023)
Introduction
Seahawk China Dynamic Fund [2022] HKCFI 1994 (date of reasons for decision: 4 July 2022)
Introduction
Up Energy Development Group Limited [2022] HKCFI 1329 (date of decision: 6 May 2022)
Introduction
The 3 core requirements are factors considered by the Hong Kong Court when deciding whether to exercise its discretion to wind up a foreign incorporated company in Hong Kong.
Ozner Water International Holding Limited (In Liquidation) [2022] HKCFI 363 (date of decision: 27 January 2022)
Hong Kong Fresh Water International Group Limited (In Liquidation) [2022] HKCFI 924 (date of decision: 6 April 2022)
Introduction
海航集团有限公司(于中国内地重整) [2021] HKCFI 2897(裁决日期:2021 年 9 月 16 日)
前言
海航集团有限公司(一家总部设在海南的大型企业,下称“公司”)的内地重整程序最近在香港获得认可。这是香港法院首次向 内地重整程序的破产管理人颁发认可令的案例。