On 26 June 2020, the Corporate Insolvency and Governance Act[1] (the Act) came into force.

The Act has significant implications for supply contracts as it will prevent many suppliers ending existing contracts once a business is insolvent. The Act will make a big impact on existing supply contracts, and will also affect the drafting and negotiation of new contracts.

We’ve all heard it said a million times - if it sounds too good to be true, it probably is. But does that age-old maxim apply to a bankrupt customer offering to pay you 100% of your unsecured claim through a “prepackaged” bankruptcy or under a critical vendor program? The answer can be complicated.

This article explores what it means to be “unimpaired” and paid in full in prepackaged bankruptcies and under critical vendor programs and outlines some of the potential pitfalls that can be faced by unsecured creditors under these scenarios.

We’ve all heard it said a million times - if it sounds too good to be true, it probably is. But does that age-old maxim apply to a bankrupt customer offering to pay you 100% of your unsecured claim through a “prepackaged” bankruptcy or under a critical vendor program? The answer can be complicated. 

This article explores what it means to be “unimpaired” and paid in full in prepackaged bankruptcies and under critical vendor programs and outlines some of the potential pitfalls that can be faced by unsecured creditors under these scenarios.

What happens if one party to a contract fails to perform? Can the innocent party get all of its losses back? What happens if the losses are difficult to prove?

Here, we look at what you can claim and how to protect your position.

The general rule

Damages for breach of contract are usually intended to compensate the injured party for its losses arising naturally from the breach or which were within the parties' contemplation when the contract was made.

In the case of William Hare Ltd v Shepherd Construction Ltd [2009] EWHC 1603 (TCC) (25 June 2009), the court declined to incorporate amendments made to an Act before the contract was signed which were not specifically referred to in the contract.

The facts