On February 27, 2018, the United States Supreme Court resolved a circuit split regarding the proper application of the safe harbor set forth in section 546(e) of the Bankruptcy Code, a provision that prohibits the avoidance of a transfer if the transfer was made in connection with a securities contract and made by or to (or for the benefit of) certain qualified entities, including a financial institution.
The Court of Appeals for the Ninth Circuit recently held that section 1129(a)(10) of the Bankruptcy Code – a provision which, in effect, prohibits confirmation of a plan unless the plan has been accepted by at least one impaired class of claims – applies on “per plan” rather than a “per debtor” basis, even when the plan at issue covers multiple debtors. In re Transwest Resort Properties, Inc., 2018 WL 615431 (9th Cir. Jan. 25, 2018). The Court is the first circuit court to address the issue.
Here the court refused to grant an injunction restraining contractor Space from presenting a winding up petition against the employer COD. The employer had failed to pay 3 applications for payment (nos.
In another case involving a winding-up petition, the petition was dismissed, after the court found there was a dispute as to whether the statutory payment scheme applied to the contract. The contractual arrangements between the parties were not formally documented, but there was a basic agreement as to the scope and price of the works, which arose out of a subcontract between Ro-Bal and main contractor McAlpines to provide fabrication and erection of steelworks at two sites. At one site the works were completed and paid for, but at the other there was a dispute regarding payment
Here the Court of Appeal granted an injunction which restrained a building contractor (Harbour View) from presenting a winding-up petition, overturning the high court's decision at first instance. Harbour View had been engaged under two separate contracts based on a JCT Intermediate WCD (2011) to carry out works at two separate sites. The employer (Wilson) failed to pay against two interim certificates (August 2013 and September 2013), leaving a sum of over GBP 1.6 million owing.