BP Canada Energy Group ULC (“BP”) has applied for leave to appeal a decision under section 13 of the Companies’ Creditors Arrangement Act (the “CCAA”) and for a stay of the orders rendered by Justice Yamauchi on April 24, 2024

Location:
Firm:

On March 23, 2020, we commented on the Quebec Court of Appeal’s decision in the Arrangement relating to Consultants SM inc. case. The City of Montreal (the “City”) appealed this decision to the Supreme Court of Canada and the appeal was heard on May 20, 2021.

On December 10, 2021, the Supreme Court of Canada (the “Supreme Court”) dismissed the City’s appeal, thereby rendering an important decision with respect to “pre-post compensation” and “non-dischargeable debts” under the Companies’ Creditors Arrangement Act (the “CCAA”).

Location:
Firm:

Le 23 mars 2020, nous avons commenté l’arrêt de la Cour d’appel du Québec dans le dossier Arrangement relatif à Consultants SM inc. La Ville de Montréal (la « Ville ») a porté cet arrêt devant la Cour suprême du Canada et l’audition du pourvoi a eu lieu le 20 mai 2021.

Location:
Firm:

On May 8, 2020, the Supreme Court of Canada (the "SCC") released its reasons for the ruling rendered on January 23, 2020, which allowed the appeal by 9354-9186 Québec Inc. and 9354-9178 Québec Inc. (collectively, "Bluberi")[1]. The SCC's ruling set aside the Québec Court of Appeal's (the "Court of Appeal") ruling, thereby restoring the first instance judgment of the Superior Court of Québec ("Superior Court").

Location:
Firm:

Le 2 décembre 2020, la Cour d’appel du Québec (la « Cour ») a rendu un arrêt important dans l’affaire Syndic de Montréal c’est électrique confirmant la décision du juge de première instance à l’effet que la Ville de Montréal (la « Ville ») ne détenait pas de sûreté sur les sommes détenues dans le compte bancaire de Montréal C’est Électrique (« MCE » ou la « débitrice »).

Location:
Firm:

On March 17, 2020, the Court of Appeal of Québec (the "Court") issued an important ruling concerning "pre-post" compensation and "non-dischargeable" debts under the Companies' Creditors Arrangement Act (the "CCAA"), by finding that the debt of a municipality arising from an agreement entered into as part of a voluntary reimbursement program ("VRP") under the Act to ensure mainly the recovery of amounts improperly paid as a result of fraud or fraudulent tactics in connection with public contracts ("Bill 26") is unsecured debt in connection with the insolvency of a co-contra

Location:
Firm:

On December 10, 2018, the Superior Court of Quebec (Court) released an important judgment concerning the assignment of contracts under the Companies' Creditors Arrangements Act (CCAA), in which the Court held that it was possible for an assignee to have contracts transferred to it without having to assume the monetary penalties arising from the assumed contracts for defaults by the assignor prior to the assignment.[1]