There have been a number of cases in recent years in which a party has sought to utilise the provisions of the CPR in order to obtain information on the opposing party's insurance arrangements, rather than waiting for that party to go insolvent in order to use the procedures provided by the Third Parties Rights Act 1930 or 2010. The recent case of Peel Port Shareholder Finance Co v Dornoch Ltd [2017] EWHC 876 (TCC) looks at this again in light of the discretion which Judges have under CPR31.16 for applications for pre-action disclosure and attempts to shut the door on such actions.
Here the court refused to grant an injunction restraining contractor Space from presenting a winding up petition against the employer COD. The employer had failed to pay 3 applications for payment (nos.
In another case involving a winding-up petition, the petition was dismissed, after the court found there was a dispute as to whether the statutory payment scheme applied to the contract. The contractual arrangements between the parties were not formally documented, but there was a basic agreement as to the scope and price of the works, which arose out of a subcontract between Ro-Bal and main contractor McAlpines to provide fabrication and erection of steelworks at two sites. At one site the works were completed and paid for, but at the other there was a dispute regarding payment
Here the Court of Appeal granted an injunction which restrained a building contractor (Harbour View) from presenting a winding-up petition, overturning the high court's decision at first instance. Harbour View had been engaged under two separate contracts based on a JCT Intermediate WCD (2011) to carry out works at two separate sites. The employer (Wilson) failed to pay against two interim certificates (August 2013 and September 2013), leaving a sum of over GBP 1.6 million owing.