A recent ruling in the Pacific Gas and Electric Company (PG&E) bankruptcy proceeding highlights the risk to certain renewable energy projects from utility bankruptcy. In a June 7, 2019 ruling, the PG&E bankruptcy court denied the claim that Federal Energy Regulatory Commission (FERC) must approve any attempt by bankruptcy courts to reject (i.e., void) power project agreements (PPAs) between renewable project owners and utilities. This is in direct opposition to a FERC ruling that it does have this power.