On 24 July 2020, the National Company Law Appellate Tribunal (NCLAT), in its decision in GRIDCO Limited v Surya Kanta Sathapathy and Others [C.A. (AT) (Insolvency) 1271 of 2019] (GRIDCO judgement), held that the termination of a Power Purchase Agreement (PPA) during the subsistence of a moratorium would be in violation of Section 14(1) of the Insolvency and Bankruptcy Code 2016 (IBC).

FACTUAL BACKGROUND

In yet another landmark decision in relation to the corporate insolvency resolution process (CIRP) of Jaypee Infratech Limited (JIL), the Supreme Court in Anuj Jain, Interim Resolution Professional for Jaypee Infratech Limited vs. Axis Bank Limited Etc. Etc. (Civil Appeal Nos. 8512-8527 of 2019) dated 26.02.2020, has laid down the law on two aspects: 

➢  the essential elements of a preferential transaction under Section 43 of the Insolvency and Bankruptcy Code 2016 (Code); and