Over the last few years, the courts have shown themselves to be increasingly unwilling to interfere in the level of liquidated damages set in building contracts. The courts have taken this position predominantly because the agreed level of liquidated damages forms part of the commercial bargain reached between the parties at the outset of the contract. However, employers should still carefully calculate the level of liquidated damages inserted into the contract for the following reasons:

Location:

The Technology and Construction Court has decided that judgment should not be stayed following a contractor's unsuccessful defence of an adjudication claim brought by its M&E subcontractor.

The case reaffirmed some key principles in assessing whether a stay is justified in adjudication enforcement proceedings: