It is fair to say that the insolvency of Carillion has sent shockwaves through the construction industry. While this may be the catalyst for change, insolvency has unfortunately been a risk which has been realised all too often. Looking at the current position, we set out the top ten issues that employers, professionals and the supply chain should consider in the event of main contractor insolvency.

The recent case of Breyer Group plc v RBK Engineering Limited considered the use of winding up petitions in construction contracts.

An application was made by Breyer to stop RBK from continuing with a petition to wind up the company. The court decided that winding up petitions can operate as a form of commercial oppression and may not be appropriate, especially when adjudication or ordinary proceedings would be a more appropriate forum for the dispute.

The background

InGrayson Consulting, Inc. v. Wachovia Securities, LLC (In re Derivium Capital LLC), 716 F.3d 355 (4th Cir. 2013), the U.S. Court of Appeals for the Fourth Circuit examined whether certain securities transferred and payments made during the course of a Ponzi scheme could be avoided as fraudulent transfers under sections 544 and 548 of the Bankruptcy Code. The court upheld a judgment denying avoidance of pre-bankruptcy transfers of securities because the debtor did not have an “interest” in the securities at the time of the transfers.

On January 10, 2012, a Florida bankruptcy court ruled in In re Pearlman, 462 B.R. 849 (Bankr. M.D. Fla. 2012), that substantive consolidation is purely a bankruptcy remedy and that it accordingly did not have the power to consolidate the estate of a debtor in bankruptcy with the assets and affairs of a nondebtor. In so ruling, the court staked out a position on a contentious issue that has created a widening rift among bankruptcy and appellate courts regarding the scope of a bankruptcy court’s jurisdiction over nondebtor entities.